王刚, 王彬, 王宝, 王闯, 穆衍清, 王柏琳, 刘青, 谢飞鸣, 李红卫, 聂小武, 卢新春. 基于“炉机对应”原则的炼钢—连铸调度模型[J]. 工程科学学报, 2013, 35(8): 1080-1092. DOI: 10.13374/j.issn1001-053x.2013.08.014
引用本文: 王刚, 王彬, 王宝, 王闯, 穆衍清, 王柏琳, 刘青, 谢飞鸣, 李红卫, 聂小武, 卢新春. 基于“炉机对应”原则的炼钢—连铸调度模型[J]. 工程科学学报, 2013, 35(8): 1080-1092. DOI: 10.13374/j.issn1001-053x.2013.08.014
WANG Gang, WANG Bin, WANG Bao, WANG Chuang, MU Yan-qing, WANG Bo-lin, LIU Qing, XIE Fei-ming, LI Hong-wei, NIE Xiao-wu, LU Xin-chun. Scheduling model for steelmaking-continuous casting process based on “furnace-caster matching” principle[J]. Chinese Journal of Engineering, 2013, 35(8): 1080-1092. DOI: 10.13374/j.issn1001-053x.2013.08.014
Citation: WANG Gang, WANG Bin, WANG Bao, WANG Chuang, MU Yan-qing, WANG Bo-lin, LIU Qing, XIE Fei-ming, LI Hong-wei, NIE Xiao-wu, LU Xin-chun. Scheduling model for steelmaking-continuous casting process based on “furnace-caster matching” principle[J]. Chinese Journal of Engineering, 2013, 35(8): 1080-1092. DOI: 10.13374/j.issn1001-053x.2013.08.014

基于“炉机对应”原则的炼钢—连铸调度模型

Scheduling model for steelmaking-continuous casting process based on “furnace-caster matching” principle

  • 摘要: 针对某特殊钢厂炼钢-连铸生产调度问题,首先,构建以炉机匹配度、连浇炉数以及过程等待时间等为主要评价指标的多目标优化调度数学模型.进而,对工艺流程结构以及炼钢、精炼和连铸三个工序的运行时间进行解析,分析合理的产品结构范围及不同产品结构下的生产组织模式.根据炼钢厂运行的"炉机对应"原则,运用柔性工序缓冲调节策略,协调优化炼钢、连铸工序间的生产节奏,求解不同生产模式下的调度方案.最后,通过仿真计算与实际生产状况的综合分析,验证了调度模型和求解策略的有效性和优越性.

     

    Abstract: Aiming at the steelmaking-continuous casting scheduling problem of a special steel plant, firstly, a multi-objective optimization scheduling model was developed, whose main evaluation indexes are furnace-caster matching degree, continuous casting heats, process waiting time, etc. Then the feasible range of product mix and production modes under different product mix conditions were analyzed by resolving the process flow structure and the operation cycle of steelmaking, refining, and continuous casting process. The scheduling problems under different production modes were solved by adjusting the operation cycle values of flexible processes on the basis of "furnace-caster matching" principle. Finally, the scheduling plans were calculated and compared with actual production data; the simulation results indicate the validity and superiority of the scheduling model and the solution strategy.

     

/